Sealing of culvert expansion joints,
tunnel and flow meter pits of left and
right shores of Khodaafarin dam

Consultant:

Mahabgods Consulting Engineers Company

Year:

2010-2011

Project Location:

Khodaafarin Dam

Operation Step:

Under construction

Project Subject:

Sealing of constructional and expansion joints having leakage in tunnels of left and right shores, top expansion joints of clay core in four openings of culverts, sealing of left and right flow meters and cracks available in horseshoe overflow     

Consumed material:

1-One component resin of Carbo Stop U, manufactured in Minova German Company

2- Two component resin of Carbo Crack Seal NV, manufactured in Minova German Company

3-Fix 10 S, manufactured in Schomburg German Company

4-AQUAFIN IC, manufactured in Schomburg German Company

5-Geofoam, manufactured in Minova and Schomburg German Companies

 

Conducted Operations are:

Regarding problems arisen from constructional stages, distributed leakages in left and right tunnels in average amount of 60 liters in second, with 2.5 bar pressure in both tunnels, also leakage in top expansion joints of clay core in every four culvert openings in average amount of 200 liters in second with 2.5 bar pressure was observed. For resolving available problems and with discarding formalities, PAM.CO Company concluded a contract with East Azerbaijan Regional Water Organization and began to work according to the following explanations:   

1-Water discharging from inside of tunnels and culvert, using several strong pump devices.

2- Opening of tunnels emergency trap-door, in 23 meter depth, carrying instruments and scaffold required materials and scaffold board to inside of tunnel and installation of scaffold at the desired places.

3-Openning on leakage places, repairing surfaces and sealing of leakages using fix 10 s special material temporarily, drilling and putting packer, injecting of one and two component resins for permanent sealing.  

4-Constructing metal mould with one side of rubber and installing them on expansion joints in culvert openings for primary sealing and preventing of injection resins pouring, up to completing the reaction time

5-Drilling, putting packer and hose inside joints for resins injection and permanent sealing of leakage places.

Volume of work:

1Number of joints having leakage has been 19 and also length of them all in all, has been 684 meter.

2-Distributed leakages in tunnel body were also sealed with presented details.